Smallwood Lake in Michigan has started refilling after work on Smallwood Dam reached substantial completion in July. The refill began on August 4 and is expected to take eight to 10 weeks. Meanwhile, work continues at Secord and Edenville dams, with Secord facing a delay after crews found a problem with a spillway gate.