The homebuyer alleged that the builder had invoked the PMRDA-PMC jurisdiction dispute only after the delay happened, using it as an excuse to explain why the flat had not been handed over to the buyer on time. The flat was priced at Rs 41.85 lakh, and the buyer had paid Rs 39.15 lakh. The remaining amount can be adjusted against the interest payable by the developer. The homebuyer alleged that the builder had invoked the PMRDA-PMC jurisdiction dispute only after the delay happened, using it as an excuse to explain why the flat had not been handed over to the buyer on time. The flat was priced at Rs 41.85 lakh, and the buyer had paid Rs 39.15 lakh. The remaining amount can be adjusted against the interest payable by the developer.
Trending
- Ukraine steps up attacks on Russian tech infrastructure, damages third data center
- Zelenskyy says ready to hold Ukraine elections if Russia offers 60-day ceasefire
- The ABCD of US politics: American-born Combative Desis face MAGA heat
- Egypt’s ancient Fayoum portraits to be exhibited abroad for first time
- Gold, silver prices next week: What investors should watch amid global uncertainty
- ‘Don’t teach us Tamil pride’: DMK hits out at Rahul Gandhi over Hindi event title
- Indian killed, 10 injured in Riyadh airport strike; chilling video shows aftermath
- Rupee relief, higher hedging costs: What RBI’s new forex rules mean